EFCOG Best Practice #33
PDF Version
Title:
Effective Use of Time Outs – A Best Practice Summary (SRS) (3/21/05)
FACILITY:
Westinghouse
Savannah River Company
POINT OF CONTACT:
Rod Hutto 803-952-9816,
rod.hutto@srs.gov
Brief Description of Best Practice:
When changing or unexpected conditions occur
during the course of work execution, including routine operations, or when
workers do not understand how to perform an activity, time outs and stop work
actions provide an opportunity to assess the situation and determine if it
impacts the hazards associated with the work. Sharing information about time
outs and stop work events reinforces management’s expectations for and support
of this important task-level safety technique and highlights the positive
effects of time outs as well as the various types of situations in which time
outs may be used, including quality assurance activities.
Why the Best Practice was used:
Although all requirements and job plans are developed with the
participation of knowledgeable personnel and may even include mockups or dry
runs, employees sometimes encounter situations in which the rules or plans
either cannot be performed at all or cannot be performed safely. Time outs
and/or stop work actions provide employees with a process to identify and
evaluate a given situation, with assistance as necessary, to determine how to
safely proceed with the work.
What are the benefits of the Best Practice:
Initiation of either a time out or stop work
is used to clarify requirements and instructions as well as to address
situations in which the rules or plans either cannot be performed at all or
cannot be performed safely. Use of time outs and stop work is promulgated to all
site subcontractors and their suppliers such that anyone performing work at the
site may use this technique.
What problems/issues were associated with the Best Practice:
Use of time outs and stop work must be
paired with adequate oversight, supervision and attention to detail for safe
work execution.
How the success of the Best Practice was measured:
The following examples highlight the value
of time outs and stop work actions when conditions warrant them and as a process
for iterative application of the ISM steps.
Description of process experience using the Best Practice:
A two-hour timeout was called in a bagless
process area when a convenience can could not be opened using normal methods.
Operations were temporarily suspended until the potential hazards that could be
encountered using an alternative opening method were adequately addressed. The
can was then opened safely.
Construction personnel working on the
Modular Caustic Side Solvent Extraction Unit project called a timeout when they
recognized the soldering they were about to perform could potentially damage
seals or fittings on an adjacent valve that was being used as a lockout point. A
failure of the valve would have compromised the safety boundaries of the
lockout. The lockout was revised to relocate the isolation point to an upstream
valve, and work resume safely.
Team members called a time out when a line
break inside a glovebag resulted in more liquid than expected. Team members
determined that the wet tap had become plugged or trash had built up in the line
to create blockage. As a result, the team determined that all line breaks
performed would have a drain and poly bottle attached to the glovebag.
Workers called a timeout during TRU
repackaging work when they observed that the streamers on the door louvers for
the truck well airlock indicated inadequate airflow. Smoke tests were performed
and the airflow issue was corrected.
An Outside Facilities team called a timeout
when they noted that a portable pump was generating more noise than previous
generators. The team contacted Industrial Hygiene to perform a noise survey, and
the procedure was revised to require hearing protection within 12 feet of the
generator when it is running.
A timeout was called after a QA Inspector
performed a material verification on a rotometer package that previously had
been approved for installation and discovered potential mechanical issues. This
action avoided the improper installation of equipment.
A Material Characterization Team called a
timeout when contamination in excess of expected levels was detected near the
room exhaust. Operations were suspended while the possible source of the
contamination was discussed. Decontamination efforts were performed before
resuming work in the area.
A deactivation team called a timeout while
X-raying dissolver equipment on the sixth level of FB Line when they discovered
that a ladder was needed to complete the work. Since there was no discussion of
ladder or possible hazards associated with ladder usage during the pre-job
briefing, it was determined that there would be a scope change if a ladder were
used. A decision was made to only perform the work that did not require a
ladder. The additional work was rescheduled for a later date.
A deactivation team called a timeout when
condensation was found in the high pressure breathing air system. All personnel
on the system exited the area and Industrial Hygiene was contacted for moisture
analysis. Normal work was resumed after the system was drained.
A timeout was called during repackaging
activities after a rigger noticed the wooden floor of an inner container had
rotted. The repackaging team attempted to slide the inner container over a skid
plate to provide additional strength during transport. A second timeout was
called when total failure of the inner container occurred during placement on
the skid plate. The team then developed a alternative method to remove the
failed inner container and its contents.
During startup of an evaporator, the feed
pump showed abnormal current readings as the flow control valve position
changed. The conductivity probe for the feed pump riser also alarmed during
attempts to flush the prime line. A timeout was taken to visually inspect the
feed pump riser, determine if the conductivity probe was in the proper location,
and revise the conductivity probe alarm response procedure to allow evaporator
restart, without taking an unnecessary risk of damaging the feed pump.
While relocating a tank riser mining tool,
personnel realized the containment sleeving arrangement could be improved to
allow workers to be positioned further from the tool during removal. A timeout
was called to revise the work planning documents and modify the sleeving. In
addition, personnel recognized the potential to cause a cooling water monitor
alarm during the work activities and took a timeout to coordinate with Canyon
personnel to prevent an unexpected alarm.
Operation personnel were preparing to
install a repair plug in a canister using a procedure that specified a small
paint brush with a lanyard attached be used to apply a thin film of fluid inside
the canister throat. However, the paint brush in the Melt Cell did not have a
lanyard and the personnel determined that the potential existed for the paint
brush to drop inside the canister, where it could not be retrieved. A timeout
was called to obtain the correct paint brush with lanyard for the job.
During set up to begin cold chemical
preparations inside a hot cell, a lab technician noticed water dripping inside
the cell from above the window. She stopped work and notified her manager since
the source of the water was unknown. It was determined that condensate was
dripping from the vent in the ceiling of the cell.
When higher-than-normal radiation rates
required recycling overheads from an evaporator back to the feed tank to flush
the system, engineering called a timeout to evaluate the quantity of liquid that
could be added safely to the feed tank without adversely impacting tank
chemistry because the evolution was expected to result in greater than normal
recycle quantities.
RadCon personnel called a timeout during a
pre-job survey before cleaning a valve house when they detected unexpected
contamination associated with a mud dauber nest. The nest was removed,
insecticide applied and the area decontaminated before work was allowed to
continue.
While performing a HEPA efficiency test, the
Maintenance HEPA testing crew took a timeout when they received readings
implying the crew was not getting the challenge aerosol into the HEPA
ventilation system. The crew notified supervision.
Workers called a timeout while removing
plastic from a tank HEPA filter containment system after surveys revealed
transferable contamination on the hut floor and HEPA filter door. The
contamination levels exceeded the RWP suspension limits for the job. Personnel
also questioned the integrity of the HEPA filter enclosure when they observed
that the bolts securing the door appeared to be loose. The HEPA housing door
fasteners and system operability were verified, the area was decontaminated, and
a surveillance schedule was implemented.
ISM Core Function and Guiding Principle to which the Best Practice relates
| Core Function 1: Define Scope of Work |
|
| Core Function 2:
Analysis of Hazards |
|
| Core Function 3: Develop and Implement Hazard Controls |
|