EFCOG Best Practice #54
02/19/08
PDF version
Title: Open Air Demolition of
Radiological Contaminated Structures (May
11, 2007)
Facility:
Hanford Site, Richland, Washington
Point of Contact:
Michael B. Lackey, P.E.,
VP of D&D, Fluor Hanford
Inc.,
509-373-9519
Michael_B_Lackey@rl.gov
Michael Stevens, PMP, Director, Central Plateau D&D and
Remediation Projects, 509-372-9078
Michael_Stevens@rl.gov
ABSTRACT:
Heavily contaminated facilities have typically required
significant decontamination to near free release levels,
prior to demolition, to prevent the spread of
contamination. These extensive decontamination efforts can
significantly increase both the cost and schedule needed to
decommission a facility. Fluor Hanford has combined both
proven processes and new techniques in innovative ways to
allow the safe demolition of heavily contaminated
facilities.
There are a variety of demolition methods that can be
combined with decontamination practices, technologies, and
fugitive dust control techniques to eliminate or
significantly reduce the potential of airborne emissions
during demolition. Different demolition methods and
fugitive dust control techniques can be implemented based on
the extent and type of contamination, the location of the
contamination within the structure, and the level of effort
of pre-demolition deactivation and decontamination
activities. In addition, airborne dispersion modeling can
be applied to a demolition project to identify the quantity,
type, or location of contaminated material that can remain
in a structure during open air demolition based on the
demolition techniques and airborne emission control methods
established. Therefore, based on a through evaluation of
the specific attributes of a structure, the nature of
contamination, and the tactical decontamination and
demolition approach, radiological contaminated structures
can be cost effectively demolished in an open air
environment.
Brief Description of Best Practice:
Open air demolition of radiological contaminated structures
at the Hanford site in Richland, Washington uses
commercially available techniques and controls to safely
conduct demolition activities in the open environment.
Based on a thorough evaluation of the type and extent of
radiological contamination in a structure, a systematic
demolition approach can be developed to reduce the potential
of generating a release of airborne emissions to a level
that allows demolition to proceed without having to install
and maintain an elaborate containment system or perform
extensive pre-demolition decontamination. The key
component to this approach is the review and understanding
of the type and location of the contamination and the
configuration of the structure. With this information, the
overall project approach can be formulated with input of the
air modeling information, deactivation and
pre-decontamination requirements, demolition techniques and
sequencing, and dust control alternatives.
Basing decontamination end points on technical requirements
such as waste acceptance criteria and dispersion modeling
rather than on emotional (that’s the way it has always been
done, or fear of the unknown) will provide defined and
defensible results.
Why the Best Practice was used:
The Best Practice of implementing open air demolition allows
for a safer work environment, reduced project costs, and
accelerated periods of performance. Therefore, identifying
and realizing best project management principles.
What are the benefits of the Best Practice:
There are several benefits associated with implementing open
air demolition of contaminated structures. The benefits
include executing the demolition task in a safer work space
configuration, reduced costs, and an accelerated period of
performance. By not having to construct an enclosure around
a structure or perform extensive decontamination,
significant ALARA, cost and schedule benefits are
immediately realized. In order to successfully conduct
demolition activities of a contaminated structure within an
enclosure many elaborate engineering, safety, and
radiological considerations have to be addressed. Examples
of these constraints include: allowing for adequate working
distances around the perimeter of the structure,
establishing areas for waste debris processing and equipment
and personnel staging areas, and maintaining safety and
radiological controls (CO monitoring, HEPA filtration,
etc.). Based on the dimensions of the structure to be
demolished, the installation of environmental controls (air
flow, filtration, heating and cooling), and the additional
footprint necessary to maneuver equipment and personnel
requires constructing an enclosure significantly larger then
the structure being demolished. The additional costs and
time requirements to plan, procure, construct, and dispose
of this type of enclosure would adversely impact almost any
project. In addition, the additional safety and
radiological risks of working within a confined work space
like an enclosure are magnified. Also, a less obvious
benefit of conducting demolition in an open air environment
is allowing all project personnel, including the owner, to
directly observe demolition activities without entering the
enclosure. This allows for a better field of view and
increased communication between field and support personnel.
What problems/issues were associated with the Best Practice:
There are several primary issues associated with performing
open air demolition. These issues can generally be divided
into two groups. The first group can be classified as
technical issues. Technical issues are typically identified
and addressed based on a rigid systematic process. Examples
of technical issues include specific details associated with
deactivation such as survey methods, identification of
process equipment, quantification of contamination, extent
and location of decontamination efforts, application of
fixatives, demolition method and sequence, air modeling,
dust control methods, personnel protective equipment (PPE),
etc. The second group consists of non-technical issues.
Non-technical issues are issues that do not address the
specifics of how the structure is to be prepared for
demolition, how the structure will be demolished, or the
specific controls to be implemented prior to or during
demolition. These types of issues consist of issues such as
work hours, lack of knowledge, or security. Although not
directly associated with the basis for implementing open air
demolition, non-technical issues can impact the ultimate
success of the project and must be considered and integrated
appropriately.
Technical issues are evaluated, analyzed, and reviewed by
the project team, consisting of project management,
engineering, radiological, safety, and supporting personnel,
to ensure that the results are justifiable and can be
implemented. In the event that the assumptions are a part
of the process, such as in developing air modeling, the
assumptions must be based on factual, historic, or
reasonable information. The outcome is typically a
conservative, but achievable or workable set of parameters
that allows for open air demolition of radiological
contaminated structures with reasonable and appropriate
controls.
Non-technical issues are a bit tougher to define and
resolve. The “lack of knowledge” for demolition was
primarily an issue with personnel not associated with the
project but in the near vicinity of the project. Using the
technical data and experience, meetings were held with
concerned personnel to alleviate concerns and answer
questions.
With any outdoor type work, the environmental elements often
dictate how a project is executed. For these projects, heat
and wind had the biggest effects on progress. The heat
required work rest regimes that, at times, precluded
appreciable progress. By shifting to a grave yard type
shift, we eliminated the heat stress issues. Wind was
constantly monitored. These projects had a wind limitation
of 19 kph (12 mph) average wind speed. At speeds over this,
the demolition was suspended and the debris piles were
sprayed with a fixative. The fixatives worked well, as
winds as high as 100 kph (60 mph) were recorded during the
demolition process.
232-Z, located in an operating nuclear facility, was veiled
in a security program that required special considerations
such as visual observations, heavy equipment controls, and
communication protocols. From a security perspective, the
open air demolition offered better observation opportunities
than say a covered area.
How the success of the Best Practice was measured:
The process success is ultimately measured by the perimeter
airborne emission and worker breathing zone data collected
during the demolition process. Based on the successful
implementation of the hazard mitigation controls, methods
and techniques, airborne emissions were significantly below
the prescribed action levels.
Description of Process Experience using the Best Practice:
At the Hanford site there have been two highly plutonium
contaminated structures demolished in an open air
environment. The two primary examples include the 233S –
Plutonium Concentration Facility and the 232Z – Plutonium
Waste Incineration Facility.
Construction of the 233S Building was completed in 1955.
From 1956 to 1965, the 233S building was instrumental in the
process of developing weapons grade plutonium. Plutonium
concentration was performed in a process cell by evaporation
and/or ion exchange treatment. The concentrated plutonium
was containerized and shipped to other Hanford facilities
for further processing. During operations, several
incidents took place resulting in the release of significant
amounts of plutonium throughout the building.
Decontamination and deactivation activities began in 1997
and were completed in 2003. During this period, the
majority of the “hold up” located in process equipment,
piping, ventilation ducting, and other miscellaneous items
were removed from the structure followed by an application
of a fixative coating to encapsulate potentially dispersible
contamination.
The 233-S Building was a reinforced concrete structure, with
a footprint of 11.3-m (37 ft) x 25.7-m (86 ft), and roof
elevations ranging from 3.7-m (12 ft) to 9.7 m (32 ft).
Concrete wall thickness ranged from 23-cm (8 in.) to 30-cm
(12 in.), and several exterior portions of the building were
made of structural steel with corrugated metal exterior
siding. The 233-SA Building, located just northeast of
233-S, was a single story, reinforced concrete structure
with 6-inch thick walls. The roof was concrete over metal
decking with insulation and built-up asphalt covering.
The 232Z Building was constructed in 1958. From 1961 to
1973 the building was used to recover plutonium through
incineration of plutonium-contaminated combustible wastes.
The building housed an enclosed system of gloveboxes, and
hoods, scrubber equipment and high-efficiency particulate
air (HEPA) filters. As with most processes of this time,
process upsets and decommissioning activities left a sizable
amount of contamination on the walls, ceiling, and floors.
The building was 11.3 m (37 ft) wide and 17.4 m (57 ft)
long. It is a single story over the process and storage
areas and two stories over the service areas at the north
end. The walls are of cinder block construction and the two
roofs are respectively 4.6 m (15 ft)and 5.8 m (19 ft) above
grade. The roofs are constructed of concrete over metal
decking with insulation and built-up asphalt covering.
In 1999, the building was determined to pose a significant
hazard and planning for deactivation and demolition began.
This facility was located in an operating nuclear facility
with hundreds of personnel located within 200 meters of the
building. The building was sandwiched between three other
buildings, the closest of which was only 4” away.
Furthermore, there was no intention of impacting ongoing
operations nor that the area and nearby buildings would be
negatively impacted upon completion of demolition.
Deactivation and demolition requirements, methods and
controls were reviewed in conjunction with air modeling
results and impacts to adjacent operating facilities. Based
on the dispersion results, it was determined that the total
mass of TRU in the building would have to one gram or less
to demolish the structure in an open air environment. This
was accomplished by removing or dismantling specific pieces
of the process system including some equipment and
ductwork. In addition, the remaining surfaces of the
interior of the structure would have to be encapsulated to
minimize it from becoming airborne during demolition
activities. An encapsulant that was used to fix
contamination levels as high as one billion dpm/100cm². For
these projects, the encapsulant Polymeric Barrier System ™
was used.
Demolition methods also had to consider the proximity of
adjacent structures (some as close as a few inches) and
methods of dust control. Due to the concern of water run
off, it was determined that dust control had to consist of
more than the typical wetting with a hose while dismantling
the building, it also would have to consist of an integrated
misting system. The misting system would consist of 3
components, a misting system installed on the end-effector
of the excavator, a misting system installed on the adjacent
structures, and a misting system installed on the building
being demolished. Therefore, based on an overall
evaluation, it was determined that with the hazards
addressed and the appropriate deactivation and demolition
controls implemented, that an open air demolition of a
plutonium contaminated structure could take place safely and
efficiently.
The planning consisted of reviewing all available
alternatives and developing the overall best practice
approach that would be safe, cost efficient, and meet the
overall project objectives. Key components to the
deactivation and demolition planning process included
characterization, air modeling, demolition methods, and
impact to adjacent operating facilities. In preparation for
characterization, the building was divided into seven
functional areas. This allowed each of the areas to be
individually characterized using a graded approach based on
the specifics of the processes, hazards, and activities that
took place in each area. Extensive radiological sampling
and NDA measurements were collected and analyzed to
determine the amount and extent of contamination. The
data was used to determine the extent and type of
decontamination work required in each functional area to
allow eventual open air demolition of the building and to
determine waste disposal pathways. Based on the modeling
data, the appropriate demolition method was identified which
allowed the buildings to be demolished without having to
fully decontaminate all surfaces.
Atmospheric dispersion modeling was conducted using
ISC3-PRIME because of its ability to model meteorological
data and adjacent obstacle wake effects specific to the
building site. The modeling was used to estimate potential
radiological contamination levels at various distances from
the building based on contamination levels and demolition
methods and controls.
The objective of the modeling was to define the potential
levels of airborne and soil exposures at surrounding control
boundaries. Potential hourly emissions rate of plutonium
were estimated for the days with planned demolition and
loading activities. An air-dispersion model was used to
compute air and surface concentration boundaries for each
day of operations, accounting for local building wake
effects, atmospheric dispersion climatology, and particle
size distribution. The modeling used hourly meteorological
data collected over ten years to examine the effects of wind
speed, direction, and stability on projected concentrations
of contaminants in the air and deposited on nearby
surfaces. Using the long-term, worst case weather averages
for the time frame of the demolition provided concise,
defendable, and conservative dispersion pattern and peak air
exposure limits.
As part of the air modeling process, several phases of
demolition were modeled such as demolition of the highest
contaminated functional area and waste loading operations.
The modeling results indicated that downwind deposition is
the main limitation for demolition of a highly
alpha-contaminated building. The main downwind deposition
contribution came from debris load out into the roll off
cans. With this information, the projects positioned control
boundaries for the demolition that provided safe operating
distances for the project workers and other operational (non
project) personnel in the surrounding area.
During the dispersion modeling for 232-Z, lessons learned
from the 233S D&D Project were used to adjust modeling
assumptions in accordance with actual data. Primary areas
adjusted included effectiveness of water misting during
demolition and effectiveness of fixative applied prior to
demolition and load out methods. After completion of 232-Z,
post modeling was performed using actual survey and air
monitoring result. Additional adjustments were identified
that will be used in future modeling to make the predicted
exposures be more consistent with the monitoring data.
Noteworthy lessons that can be applied to future demolition
activities are key to improving on the existing process.
The lessons found to be noteworthy are provided below.
-
Fixative
Applications are Effective
– The fixing any smearable or removable contamination
prior to the start of demolition proved effective.
Furthermore, the fixatives applied during demolition, kept
contamination locked down during loading and periods of
inactivity.
-
Picking out a
building among other buildings is difficult and more
costly – Selective
demolition is more costly and time consuming due to
adjacent facility protection, radiological contamination
spread concerns, protection of non-demolition personnel,
and mobilization/de-mobilization.
-
Waste Disposal
Options tends to be limiting factor versus Dispersion
Modeling Limitations -
In these demolition projects the Waste Acceptance Criteria
of the onsite disposal facility was more limiting than the
dispersion limitations.
-
Misting Devices and
Water are Effective at Controlling Contamination – The
misting devices on and surround the building and on the
shear controlled the dust and contamination. The fine
mist performed well at capturing airborne particles and
keeping them within the confines of our radiological
boundaries. One down side to the misting is that during
breezy periods, the effectiveness is reduced.
-
Dispersion Modeling
Helped in Setting Radiological Boundaries and Provided a
“Level of Comfort” for Plant Personnel
– The dispersion modeling supported our efforts to perform
open air demolition, helped in setting boundary locations,
picking demolition methods, and provided a “level of
comfort” based on hold up and demolition methods. The
modeling tends to be conservative; however, the project
did revise the modeling inputs based on actual conditions
for future use in dispersion modeling.
-
Removal of Highly
Contaminated Debris Before the Remainder of the Building
was Demolished Greatly Reduced the Potential for
Contamination Spread - By
removing/packaging the highly contaminated material
contained in the building before demolishing the remainder
of the building reduces the potential for contamination
spread, the contamination of the demolition equipment, and
airborne concerns.
Conclusion:
Open air demolition without decontamination to free release
or near free release criteria, is safer, more cost effective
and faster. Using conventional techniques and equipment in
innovative ways produces tangible results.
|