|
EFCOG Best Practice #60
(12/17/08)
PDF
Version
Title:
Construction
Specifications
Facility: Los Alamos
National Laboratory, West Valley Demonstration Project
Point of Contact:
Tim J. McEvoy, 505-667-8172,
mcevoytj@lanl.gov; or Bob Carter, 509-377-3220,
bob.carter@wch-rcc.com
Brief Description of Best Practice:
Maintaining Accurate and Up To Date
Construction Specifications
1. Up to date references
A simple matrix (in the
form of a spreadsheet or database) can be developed that
cross-references the specifications and the references (e.g.
codes and standards) listed in each (see table 1.1 below for
an example). With this type matrix it is clear what
specifications need to be updated when a reference changes.
There is some initial cost to develop a matrix but the
increased efficiency of the change process and cost savings
from avoiding change orders and schedule delays more than
compensates for the development costs.
|
Specification Section |
ACI 319 |
ACI 341 |
ACI 301 |
ACI 347 |
ASTM C 1260 |
ASTM C 94 |
ASTM C 142 |
ASTM C 39 |
AASHTO 303-00 |
|
03 1512 |
X |
X |
X |
X |
|
|
X |
X |
|
|
03 1534 |
X |
X |
|
|
|
X |
X |
X |
|
|
03 1550 |
|
|
X |
X |
|
|
X |
X |
X |
|
03 3001 |
X |
X |
X |
X |
X |
X |
X |
X |
X |
|
03 3053 |
X |
|
X |
|
|
|
X |
X |
X |
Table 1.1 Specification/Reference Matrix
2. Accurate account of submittals
Each specification or procurement document
should clearly identify the required submittals by listing
all of the required submittals for that section. This allows
the subcontractor to quickly determine the type and number
of submittals required and also allows improved tracking of
submittals by the owner. In addition, submittals should be
divided into two categories, those that are reviewed and
approved and those that are records of activities performed
(see table 2.1 for an example).
|
Document Category Number |
Specification Paragraph Reference |
Document Description |
Permission to Proceed Required |
Submittal Schedule (per Section 01300 para. As
shown) |
Quantity Required |
Kind of copies |
Remarks |
|
Yes |
No |
|
Init |
Final |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table 2.1 Engineering Document Requirements
Why
the best practice was used:
Inaccurate or out-of-date construction
specifications references can add a potentially significant
cost and schedule burden (e.g. rework, nonconformances, and
work delays) to projects and adversely affect the quality of
the final product.
What are the benefits of the best practice:
Clearer interface with subcontractors and
suppliers to ensure design and quality expectations are
specific and there is little room for interpretation that
could result in less that expected item or activity quality.
What problems/issues were associated with the best practice:
Ensuring that subject matter experts developing the matrix
had access to the most recent revision or addenda of the
available codes and standards. Access to these codes and
standards requires keeping an up to date library that may
come with a price for membership or distribution listing.
Again the savings for doing it right the first time will out
weigh the cost. Consider one company library with access for
employees needing this information to save on cost of
multiple libraries.
How the
success of the Best Practice was measured:
Verifying the cost of delays from projects
not using the latest codes and standards to projects that
did it right the first time. The positive difference in cost
and schedule are very noticeable for the bottom line.
Description of process experience using the Best Practice:
Early in a relative large construction
project a nonconformance was written on conduit over fill.
The contractor insisted that their design organization used
the National Electrical Code (NEC) calculations. After
several days of discussion it was learned that the NEC
software used by the design organization was four years out
of date and the calculation tables had been revised in the
NEC. Up to date NEC conduit fill software was installed and
the remainder of the project went smooth. A new (larger)
conduit was installed to correct the original issue. Had
this issue not been corrected early in the construction
process one could see how expensive this mistake could have
been. Using this best practice to ensure that the codes and
specifications reference including the most up to date
revisions has prevented other such issues. |