|
EFCOG Best Practice #67
(07/09/09)
PDF
Version
Title:
Providing Operations-Focused
Environmental Regulatory Guidance to Enhance Operational
Ownership and Regulatory Compliance
Facility:
U S Department of Energy, National Nuclear
Security Administration, Pantex Plant
Point of Contact: Bob Roulston,
806-477-6675,
rroulsto@pantex.com
Brief Description of Best Practice:
A
Senior Manager-level memo (known as an Air Quality
Management Requirement [AQMR] memo) is developed by the
Regulatory Compliance Department (RCD) Air Quality team. The
memo identifies:
-
The
Basis for the regulatory
authorization that allows a specific emission unit or
group of units to emit air contaminants (referencing any
representations made to the regulatory agency that would
be considered an enforceable basis for obtaining the
authorization);
-
Scope
of the authorization – what units/activities/locations
are authorized;
-
Administrative Requirements:
what is expected of management to incorporate
requirements in procedures and assure compliance;
-
Reporting Requirements:
what records to maintain, when/what/how to file reports
for compliance demonstration (performed monthly for most
operations);
-
Notification and Follow-up:
What will happen when the reporting is submitted,
particularly when activities may approach regulatory
limitations?
Why the best practice was used:
-
Historically, Pantex operational
groups perceived that management of ‘environmental
compliance’ was the duty of the RCD, rather than an
aspect of operations that they needed to manage.
This attitude was consistent
with other attitudes regarding ‘safety’.
-
The RCD identified a need to
‘engage’ Operational groups in planning and maintaining
regulatory compliance.
Those groups ‘owned’ the
process, and only they could make compliance a leading,
rather than a trailing, aspect.
-
This ‘engagement’ had to recognize that:
-
Both Operations and RCD personnel had knowledge that
needed to be understood by the other group;
-
Operational processes had to be understood by the
RCD personnel in order to identify the scope of
environmental regulatory requirements applicable to
the processes;
-
Compliance requirements had to be communicated in a
way that made sense to the Operational manager
(following the K.I.S.S. principle whenever
possible);
-
The communication had to be sustained within the
company – it had to be process, not expert,
maintained.
What are the benefits of the best practice:
-
Operations
managers have a single reference document to use when
planning and maintaining activities;
-
Operations
Managers assure that emissions are regularly reported
and evaluated;
-
As personnel
change, there is continuity for demonstrating compliance
with regulatory requirements;
-
Development of an
AQMR and issuance requires the regulatory compliance
specialist to work with the Operations personnel – both
parties become better informed of how each works to
enable the plant to succeed.
Reporting requirements are
tailored to the Operations group, and in many instances
require them to use data that would have been available
without the development of the regular reporting
requirement.
What problems/issues were associated with the best
practice:
-
Organizational Authority:
Initially, memos were issued by a compliance section
manager to the manager of the section conducting the
emitting operation.
This approach did not
establish sufficient authority to ensure that practices
were implemented and maintained.
This has been resolved by
having the documents issued on a senior management level
(Division Manager), with copies routed to lower
echelons.
-
Reporting
(format and buy-in):
When initially developed, reporting
was required, but there was no specific format reports
were expected to follow.
Reports came in as e-mails,
hard-copy documents, spread-sheets; all of which
required substantial time for RCD personnel to review,
capture and transfer necessary data for demonstration of
compliance on both operational and site-wide purposes;
and then verifying that compliance was being achieved.
-
First, a
system-wide mail box was established in the plant
e-mail system – reporting requirements were changed,
directing that all reports were to be submitted to
this box, rather to specific individuals.
-
Next, RCD began issuing ‘tasks’
through one of the site’s work management programs,
setting delivery dates for submittal of the reports.
The air team, and plant
management, thus monitored the completion and
submittal of the reports – making operational
personnel and their line management aware of the
need to complete the reports,
-
The air team in the past few
years has internally developed a family of Microsoft
Excel work-books that allow operational supervisors
or their designees to enter the operational data or
chemical use data that is used to calculate
emissions, perform the emission calculations,
approve that the data has been entered and verified
by operations, and provide a summary compliance
report for that operation detailing compliance for
the reported month, for the past 12 months, and
projections on the extent of operations that may be
performed in the next month that will be ‘in
compliance’.
The air team has
approval authority control of access to these work
books.
-
The air team then developed a
‘roll-up’ workbook that captures the data from all
these operational work books for a site wide report.
These reporting upgrades
have significantly reduced the time needed,
site-wide, to
prepare
a summary for management review.
How the success of the Best Practice was measured:
-
Pantex initiated the process of
using Air Quality Management Requirement (AQMR) memos in
the late 90’s.
-
Pantex has not experienced a notice of deficiency/
notice of violation from an air quality inspection since
2001;
-
Pantex has successfully managed emissions records to
support its continued status as an “Air Synthetic Minor”
facility, under the Federal Operating Permit program;
-
Comments from operational users acknowledging their
responsibilities, including the ease of transferring
reporting duties as the organization has changed.
Description of process experience
using the Best Practice:
The
process is designed along the lines of the ‘Quality Circle’
used by the ISM process.
-
Identify Scope: Generally, a
potential new or modified source of air emissions is
identified during a NEPA review.
-
Identify Hazards: If there are any
regulatory requirements that will impact the design or
operation of the new process, they are identified at
that time, or as soon as information is available.
-
Identify Controls: Applications or registrations are
prepared, along with the AQMR document, telling
operators what must be done to stay in compliance.
-
Implement Controls: Get the registration/permit formally
submitted, approved and documented; develop and issue
the AQMR.
-
Perform the Work: Operations personnel perform work and
submit monthly activity/emission reports.
-
Evaluate: On-going process of Operator/RCD contacts to
assure the appropriate personnel are submitting,
approving and reviewing reports, to identify
opportunities for improvement or changes in processes
that need further evaluation.
The Regulatory Compliance Department is
issuing similar memos for all processes evaluated for air
emissions, even when there are no air quality regulatory
requirement, in order to document all process reviews.
We believe that B&W Pantex needs
to provide timely, positive demonstrations that potential
emissions sources have been evaluated, identified for
necessary controls, controls implemented in advance of
process start, verified that controls are adequate.
|