DOE
Complex Electrical Event Charts
July 2007
Office of Science (SC Program Office) charts have been added to
this package, by request of the EFCOG team.
The
grand total events chart over the entire DOE complex has lost some
of the initial decrease shown from October 2006 through March
2007. The last four months appear to have returned to the
previous baseline of 15 events per month, but this is not yet a
statistically significant increase.
There
is a nearly significant increase in Electrical Shocks (keyword
08A) over the past 2 months over the DOE complex. There have been
9 over the course of the past two months, compared to the improved
baseline of 1.8 per month (Jun 06 - Mar 07). The nine occurrence
reports are:
EM-SR--WSRC-FSSBU-2007-0003
NA--LASO-LANL-BOP-2007-0012
NA--LASO-LANL-BOP-2007-0013
NA--LASO-LANL-FIRNGHELAB-2007-0001
NA--LASO-LANL-TA55-2007-0022
NA--NVSO-NST-NLV-2007-0003
NE-ID--BEA-ATR-2007-0012
NE-ID--BEA-CFA-2007-0002
SC--BSO-LBL-EETD-2007-0001
Electrical
Events ORPS by Month All DOE
08A Electrical Shocks
ORPS by Month All DOE
08J Electrical Near
Miss ORPS by Month All DOE
08J Electrical Near Miss
- Top 7 Causes, All DOE
Electrical Events ORPS by Month SC Program Office
08J Electrical
Near Miss ORPS by Month SC Program Office
08A Electrical
Shocks ORPS by Month at SC Program Office
Electrical Events ORPS by Month NA Program Office
08A Electrical
Shocks ORPS by Month at NA Program Office
08J Electrical
Near Miss ORPS by Month NA Program Office
Electrical Events ORPS by Month EM Program Office
08A Electrical
Shocks ORPS by Month at EM Program Office
08J Electrical
Near Miss ORPS by Month EM Program Office
For more information on Statistical Process
Control, please see
http://www.hanford.gov/rl/?page=1144&parent=169
or contact Steve Prevette at Fluor Hanford at
steven_s_prevette@rl.gov
|