DOE Complex Electrical Event Charts
August 2009
10/22/09
Analysis of EFCOG Electrical Safety Charts for
August 2009
SC Program Office total events is stable on the
current baselines.
NA Program Office 08J Electrical Near Misses was
greater than seven months in a row above average, but July and
August did return to zero. A new average and control limits
will be developed when the data stabilize.
EM Program Office charts are stable on the
current baselines.
All other charts are stable on their current
baselines.
A3B1C03 Incorrect performance due to mental lapse
continues to be the leading cause of events for the past 12
months.
Raw Data Sheet
Electrical Events ORPS by
Month All DOE
08A Electrical Shocks ORPS by
Month All DOE
08J Electrical Near Miss ORPS by
Month All DOE
08J Electrical Near Miss - Top 7
Causes, All DOE
Electrical Events
ORPS by Month SC Program Office
08A Electrical Shocks ORPS by
Month at SC Program Office
08J Electrical Near Miss ORPS
by Month SC Program Office
Electrical Events ORPS
by Month NA Program Office
08A Electrical Shocks ORPS by
Month at NA Program Office
08J Electrical Near Miss ORPS
by Month NA Program Office
Electrical Events ORPS
by Month EM Program Office
08A Electrical Shocks ORPS by
Month at EM Program Office
08J Electrical Near Miss ORPS
by Month EM Program Office
For more information on Statistical Process
Control, please see
http://www.hanford.gov/rl/?page=1144&parent=169
or contact
Steven S Prevette
Fluor
Government Group
Savannah River Nuclear
Solutions
Steven.Prevette@srs.gov
|