Analysis of EFCOG Electrical Safety Charts for March 2010

An increased baseline average and control limits have been calculated for the DOE 08A Electrical Shocks reports due to the previously noted increasing trend.

Electrical Shocks and Near Misses 08J across DOE are now seven months in a row above average, a significant increasing trend.

SC Program Office charts are stable. 

NA Program Office Electrical Events and 08J Near Misses appear to be stable.  NA Program Office 08A Electrical Shocks have been elevated since October 2009 and will have a new baseline average and control limits calculated if the data stabilize at this higher level. 

EM Program Office Electrical Events is one month away from an increasing trend.  The past three months have been one standard deviation above average. 

EM Program Office 08J Electrical Near Miss Chart continues to have an increasing trend, with more than four of five months have been one standard deviation above average.  In the past six months there have been eleven events, as compared to only four reports in the previous eleven months.

EM Program Office 08A Electrical Shocks for February was above the UCL with three reports, but March did return to zero.

All other charts are stable on their current baselines.

Causes A3B1C03 – “Incorrect performance due to mental lapse” and A4B1C01 – “Management policy guidance / expectations not well-defined, understood or enforced” are now the top two leading causes of Electrical Near Misses over the past 12 months.

Raw Data Sheet

Electrical Events ORPS by Month All DOE

08A Electrical Shocks ORPS by Month All DOE

08J Electrical Near Miss ORPS by Month All DOE

08J Electrical Near Miss - Top 7 Causes, All DOE

Electrical Events ORPS by Month SC Program Office

08A Electrical Shocks ORPS by Month at SC Program Office

08J Electrical Near Miss ORPS by Month SC Program Office

Electrical Events ORPS by Month NA Program Office

08A Electrical Shocks ORPS by Month at NA Program Office

08J Electrical Near Miss ORPS by Month NA Program Office

Electrical Events ORPS by Month EM Program Office

08A Electrical Shocks ORPS by Month at EM Program Office

08J Electrical Near Miss ORPS by Month EM Program Office

 


For more information on Statistical Process Control, please see http://www.hanford.gov/rl/?page=1144&parent=169 or contact

Steven S Prevette

Fluor Government Group

Savannah River Nuclear Solutions

Steven.Prevette@srs.gov

 


EFCOG POC

DOE POC

Mark Mcnellis, SNL - Chair

Electrical Safety Program Manager

Sandia National Laboratories
Po Box 5800
Albuquerque, NM  87185-1094

Phone: 505-845-4895  

E-mail: msmcnel@sandia.gov


Jackie McAlhaney, SRNS -
Vice Chair

Technical Advisor

Savannah River Site
Building 703-H 
Aiken, SC 29808

Phone: 803-208-3389 

E-mail: jackie.mcalhaney@srs.gov

 

David Mills, SRNS - Secretary

Chair, Senior Electrical Review Board

Savannah River Site

Bldg. 707-38B, Room 8

Aiken, SC / 29808

Phone: 803-952-8295

Email: tdavid.mills@srs.gov

 

Frank Russo, DOE-HQ/NNSA
NNSA/DOE
1000 Independence Ave
Washington, DC   20585

Phone: 202-586-9056

E-mail: frank.russo@nnsa.doe.gov